Viewing inquiries for 06-0E3504

Submit new inquiry for this project


Inquiry #1: Please Confirm that the Rock Blanket Falls Under Section 20-5.03 INERT GROUND COVERS AND MULCHES, and Sub Section 20-5.03A(3)(b) Earthwork, that states "Maintain the planned flow lines, slope gradients, and contours of the job site. Grade subgrade to a smooth and uniform surface and compact to at least 90 percent relative compaction."
Inquiry submitted 03/24/2017

Response #1:Submitted for consideration.
Response posted 03/27/2017






The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, “JOB SITE AND DOCUMENT EXAMINATION” of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.